New York City’s gas ban is Local Law 154 of 2021. It bans burning any fuel that emits more than 25 kg of CO₂ per million BTU in new buildings. In practice that rules out natural gas, propane and heating oil for heating, hot water, stoves and dryers. What counts is the date you file your first DOB New Building (or Alt-CO New Building) application. Buildings under seven stories filed since January 1, 2024 must be all-electric. Every occupancy, including central hot water, must comply for filings from July 2, 2027. Affordable housing gets extra time. Existing buildings are not covered. A federal appeals court upheld the law in June 2026. If you’re filing now, design all-electric unless your space fits a named exemption.
Which deadline applies to my project?
The deadline is set by the filing date of your initial GC application in DOB NOW. If it’s filed on or after the compliance date, the whole application has to comply. A major redesign that needs a new application is judged by the new filing date, according to the DOB’s LL154 FAQ.
| Applications filed on or after | Covered buildings |
|---|---|
| January 1, 2024 | 1–2 family homes (R-3) and all occupancies under 7 stories, not counting service hot water |
| December 31, 2024 | NYC School Construction Authority projects |
| December 31, 2025 | Affordable housing under 7 stories, not counting service hot water |
| July 2, 2027 | All occupancies, including service hot water |
| December 31, 2027 | Affordable housing 7 stories or taller, including service hot water |
“Affordable housing” here means 50% or more of the units are under a regulatory agreement or similar instrument. Each building is judged separately, so multiple buildings on one lot are not combined.
Does it apply to renovations and existing buildings?
Usually not. The law covers new buildings and alterations filed as New Buildings. Under the DOB FAQ:
- Existing buildings can switch from oil to gas.
- Utilities can upgrade gas service for existing accounts.
- Subdividing an existing building into more units with new meters is not covered.
- An alteration that increases floor area by more than 110% cannot get gas service.
Existing large buildings still fall under Local Law 97, which sets carbon caps for most buildings over 25,000 square feet. LL97 doesn’t ban gas, but its caps tighten in 2030. Gas equipment installed in a renovation today will count against those caps.
What is exempt?
The DOB lists these exceptions:
- Buildings a regulated utility uses to generate energy
- DEP facilities that treat sewage or food waste
- Specific spaces that need combustion for manufacturing, laboratories, laundromats, hospitals, crematoria or commercial kitchens
- Emergency or standby power
The exemptions apply to specific spaces, not whole buildings. A mixed-use building with a restaurant can keep gas for the commercial kitchen, but the apartments above still need electric heat, hot water and cooking. Plan the gas service, metering and venting for the exempt space only. Assume an examiner will ask you to justify the need for it.
Is the ban legally settled?
For New York City, mostly yes. On June 30, 2026, the Second Circuit ruled 3–0 that neither Local Law 154 nor the state’s companion law is preempted by the federal Energy Policy and Conservation Act. The court held that the laws regulate which fuel an appliance uses, not its efficiency (Second Circuit opinion). The Ninth Circuit ruled the opposite way when it struck down Berkeley’s 2019 gas hookup ban in 2024. The resulting circuit split makes Supreme Court review more likely than usual. The city’s law has been enforced since January 2024 throughout the litigation.
The statewide All-Electric Buildings Act is a separate law. It was due to cover buildings of seven stories or fewer starting January 1, 2026, and larger buildings from 2029. The state agreed to pause it in November 2025 while the appeal was pending. As of November 2026, the New York Department of State says a court order still suspends enforcement. A Supreme Court petition would extend that pause. That matters for projects in Westchester, Long Island or upstate. It does not change anything inside the five boroughs.
What changes in design and budget?
- Space heating and cooling: Air-source heat pumps such as VRF systems, packaged terminal heat pumps or ducted split systems replace boilers and furnaces. Cold-climate models are rated to heat at outdoor temperatures well below 0°F. Size the system at the design temperature, not at its nominal rating.
- Hot water: This is the hardest part in tall buildings. That’s why the DOB gave service hot water until July 2027. Central heat pump water heating needs roof or mechanical-room space, storage tanks and careful recirculation design. Lock in the space early, before the architecture is fixed.
- Cooking and laundry: Residential units get induction or electric ranges and heat pump or electric dryers.
- Electrical service: Removing gas moves the whole heating load onto the electric service. Request Con Edison service early. Service lead time and transformer vault location can drive the schedule more than any mechanical choice.
- Envelope: Better insulation and airtightness shrink heat pump size and service size. On all-electric projects this usually saves money overall, not just energy.
Most of the cost difference comes from hot water, electrical service upgrades and the space the equipment takes up. Removing gas piping, flues and meters takes some cost back out. The net figure depends on building height, unit count and how early the design accounted for electrification. It costs far more to switch a design that started on gas than to plan all-electric from the beginning.
Which incentives are still available?
Several programs cited when the law passed have shrunk or ended:
- Federal 45L credit for energy-efficient new homes: the 2025 budget law (the One Big Beautiful Bill Act) ended it for homes acquired after June 30, 2026, per the IRS.
- Federal 25C credit for home efficiency improvements: ended for property placed in service after December 31, 2025.
- NYS Clean Heat: The utility rebate program stopped paying for new construction that is legally required to be electric, and no longer covers air-source heat pumps on those projects. Ground-source heat pumps and heat pump water heaters still qualified as of the December 2025 program update.
The free NYC Accelerator advisory service and NYSERDA’s New Efficient Homes heat pump incentive are still worth checking. Don’t build incentive money into your pro forma until you have current eligibility rules in writing.
Why the city did it
Buildings produce more than two-thirds of New York City’s greenhouse gas emissions, according to the DOB. Fuel burned on site for heat and hot water is a large share of that. Stopping new combustion equipment from going in avoids adding gas systems that would later have to be retrofitted to meet LL97 caps and the state’s 2050 climate targets.
Before your next filing, check your GC filing date against the table above. Then decide whether any space qualifies for an exemption and document why. Bring the electrical engineer and Con Edison in at schematic design, not after the mechanical layout is set. If you’re building outside the city, watch whether a Supreme Court petition keeps the state law on hold before you commit to gas.